SUPER RENO TYPE:
VILLA STYLE 1900's – Mid 1950's

NOOOOOO! WONT DO THIS APPROACH, a big rabbit hole here lol...
Too long, too boring... too already available lol

Much better utilising our Partners/Participants etc and making things more accessible with links to stuff like this

Considering the large number of villas constructed, there was a wide variation in construction details and materials used, so careful site investigation is always recommended.

Review the state of the existing building, identify the problems and work out what you want to achieve and how you want to live – within your budget!

TYPICAL PROBLEMS:

TECHNICALLY SPEAKING

An introduction for this more TECHNICAL SECTION This will be more about detail and include various links to valid aspects etc. This is the section that will need to be updated on a regular basis.

...Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

DESIGN

Consider the original design and layout (& any subsequent alterations) which may or may not include:


FOUNDATIONS & SUBFLOORS

Old villas may have uneven/non level floors.

The earliest New Zealand homes were generally built on flat, good bearing capacity land, but as our cities expanded and the suburbs crept into the surrounding hills, onto reclaimed land or onto drained, swampy areas – the ground's bearing capacity was compromised.

As part of a general inspection, all floors should be checked to make sure that no movement has occurred. In most instances of foundations failure, the signs will be obvious in the unevenness of the floor.

Look out for:


BAD GROUND: More infrequently, uneven floors may be due to subsidence of the foundations because the home was built on unstable ground such as: deep organic topsoil, peat, soft or expansive clay, uncompacted fill.

In these cases, it's likely that the heavier elements, such as chimneys, masonry and brick walls may have sunk, cracked and be out of plumb. In cases of subsidence, obtain the advice of a qualified structural engineer.

LEVELLING: The most effective way to correct a floor that is out of level is to employ a firm experienced in this work to jack the sunken parts of the building back to as near level as possible. The piles and/or damaged subfloor can then be replaced to reinstate the building in the level position.

RONNIE, below is just a wee example of potential pull out video within the technical section. In this case it's a video, but will do a similar one for links to other sites etc. I actually know this chap and he could be VERY useful re the Reno Guide, will chat with Bob.



This process may result in consequential damage to wall linings. In some cases, doors and windows will need to be eased as the building sank and will require remedial work after the jacking. An assessment must also be made of the effect of jacking on additions, alterations, fittings and services added to the building after the floor sank.

IF JACKING IS NOT POSSIBLE: The floor may be left as it is, if acceptable to the owner, overlaid by a new timber, plywood or particleboard floor packed up level, or where there's a “hump’ in the middle of a room, it can be levelled by removing the centre piles and allowing the centre of the floor to settle with the perimeter walls.


REPILING

Rotted timber should be replaced with H5 treated timber or precast concrete piles.

New treated timber or concrete piles can be installed:


When replying in soft ground, it's sometimes necessary to install deeper piles in order to reach firmer ground. These can be small diameter steel rails that are coated to resist corrosion. They are driven or augured down to the required level and then a concrete pile is cast around the top. In extreme cases where the house is built on deep unstable ground, it may be necessary to remove the roof so that the long piles can be driven down to firmer ground.

Soft ground conditions are usually the result of wet soils so the renovation needs to address the cause of the dampness. Once the soil dries, bearing should return, but sometimes it may be necessary to install additional bearer to remove the load from the offending pile.

If there's a gap between the pile and the bearer or both are basically sound but thee's signs of moisture on the bearer, the bearer can be jacked up off the pile (after cutting any fixings), a DPC inserted into the space and the bearer lowered and refined.

Repiling carried out since the 1920's and before the introduction of H5 treated timber is likely to be concrete piles with the bearers tied with galvanised wire to the concrete pile. Any original connecting wires are likely to be corroded and of limited structural value – so replacement will be required.


INADEQUATE FOUNDATION BRACING

Section 5 of NZS 3604 requires foundations to be adequately braced but existing foundation designs may not comply with this requirement. It's likely that a significant number of villas will have already been replied, although some with original foundation remaining. Typically, when a villa was repiled (certainly if done pre-1980's), it was unlikely support or bracing was provided to the new piles.


Bracing can be provided by a combination of:

With most suspended floor construction, it's possible to provide diagonal braces between adjacent piles or between piles and bearers/joists. Modern 12kN pile fixings may be able to be used, or the connection can be made with M12 hot-dip galvanised bolts. Another option is to embed a number of piles more deeply into the ground, typically 900mm for an anchor pile in accordance with NZS 3604 – how many depends on the size of the house and the local earthquake and wind zone.

If a floor is springy because the span is too large for the timber sizes, a new bearer and piles at mid-span can be added to provide more support. For first floors, the installation of support beams can be one option, but this must be integrated with structural changes to the ground floor where the plan of the building is being modified.



INSUFFICIENT GROUND CLEARANCES

Many villas are built much closer to the ground than permitted by the current Building Code. While the original villa may have sufficient clearance, it's common for the clearances to be significantly less under the lean-to addition (especially on a site that slopes to the front of the house).

A lack of ground clearance may not cause a problem provide the soil under the villa is dry and/or if there's sufficient ventilation.

Renovation options to address lower than minimum ground levels can include:

Ronnie, this does on for a lot, need to discuss how this sort of thing is handled. If we do actually use BRANZ, we should obviously acknowledge, but obviously all information will need to be updated!




Superhome Design Guide © 2024